5. Entering Data: Updates to HUD Verifications
When a client reports a change in their circumstances, the change needs to be documented on the date it is reported. Changes that need to be recorded include Housing Move-In Date (for RRH/PSH), changes to Health Insurance, Income, Non-Cash benefits or Disabilities during a project stay.
Creating an Interim Review
- Click on the Interim icon within the row for the project
Click Add Interim Review
- Check all household members included for the update
- Select Interim Review Type (select Annual Assessment only when the assessment is within the 30 day window of the anniversary date)
- Confirm the Review Date
HUD Verification - Health Insurance and Non-Cash Benefits
- Verify Covered by Health Insurance or Non-Cash Benefits change if needed.

- Click the magnifying glass icon to open all the previous records.
- From the HUD Verification table, click on the pencil next to the type of insurance benefit that is changing. The record that opens is the last known open response.
- Click the pencil by the source that has changed.
- Add the End Date. The End Date should be the day before the Interim Review Date. Example: This Client's Interim Review is dated 9/12/2026, so the End Date for this record is 9/11/2026 - the last date this "No" response was valid.
- You should not change any other information; just add the end date and press Save.
-

- The set of records now shows an end date for the source that has changed.

- Click Add to create a new record that will show what the client is currently receiving.
- Select the insurance type that the client is now receiving.
- Covered: Yes
- Save

Be sure to complete all necessary changes before exiting the assessment.
Make sure the HUD Verification has a green checkmark

This same process is used to update Non-Cash Benefits. Disability and Income have slightly different processes as outlined below.
HUD Verification - Disabilities
If a client's disability status needs an update it needs to be changed from the date
Distinction:
- The question 'Does client have a disabling condition" needs to be changed from the project start date
- The HUD verification update will be changed from the Interim Assessment.
Follow these steps if the disabling condition question needs to be changed:
- Click on the Project Start Date pencil
- Change the response
- Scroll to the bottom of the assessment and click Save
- You will need to delete any previous responses to the disability question
-
Go back to the Disability question and click the bar by the question
- Click the trash can by any answers other than the top row response (if you cannot click a trash can icon reach out to wyhelpdesk@icalliances.org for assistance)
- Scroll to the bottom of the assessment and click Save & Exit
Next, you will update the HUD verification on the Interim review. Note: the backdate should be set to date of the new information.
- Scroll to the Disability HUD Verification table.
- Click the magnifying glass icon to open all the previous records.

- Click on the pencil next to the Disability that is changing.

- Add the End Date. The End Date should be the day before the assessment Interim Review Date. Example: This Client's Interim Review is dated 9/12/2026, so the End Date for this record is 9/11/2026 - the last date this "No" response was valid.
- You should not change any other information; just add the end date and press Save.

- The set of records now shows an end date for the source that has changed.
- Click Add to create a new record that shows what the client is currently reporting.

a. Select the Disability Type that is being updated.
b. "Disability Determination": If the client reports having a disability, the response for this is Yes. Only Permanent Supportive Housing is required to verify the disability.
c. "If yes, Expected to be of long-continued and indefinite duration and substantially impairs ability to live independently": unless this is a temporary condition the response is Yes
d. Save

Be sure to save the whole assessment when completely finished with all updates!

Make sure the HUD Verification has a green checkmark

HUD Verification - Monthly Income
From the HUD Verification table, click on the pencil next to the Income that is changing

- Click the pencil by the source that has changed.

- Add the End Date. The End Date should be the day before the Interim Review Date. Example: This Client's Interim Review is dated 9/12/2026, so the End Date for this record is 9/11/2026 - the last date this "No" response was valid.
- You should not change any other information; just add the end date and press Save.
- The set of records now shows an end date for the source that has changed.
- Click Add to create a new record that shows what the client is currently receiving.

a. Select the Income that the client is now receiving
b. Monthly Amount: fill in the amount
c. Source of Income: select the source that the client is receiving
d. Receiving income: Yes
e. Save

Be sure to save the whole assessment when completely finished with all updates!
Make sure the HUD Verification has a green checkmark